A black frame is bare walls and a floor slab with no services; a white frame is plastered, screeded and has wiring and plumbing roughed in, but no finishes; a green frame is a white frame with some of the finishes done, and developers hand over different things under that name. On the SIVRCE price list, finishing 65 m² from a white frame costs about 574 ₾/m², from a black frame about 885 ₾/m² (Standard grade).

Three states in one table

"Black" and "white" frame are the language of new builds in Georgia: it is how developers sell apartments and how contracts describe them. The words are short, but each one stands for a specific list of works — and that list decides what the renovation costs.

StateWhat is already thereWhat is left
Black framebare walls and slab, no servicesEverything: partitions, wiring, plumbing, plaster, screed, waterproofing and all finishes
White frameplastered, screeded, services roughed in — no finishesFinishes: skim coat, paint, flooring, tiles, doors, sanitaryware and sockets
Green frameA white frame with some finishes — developers hand it over in different statesWhatever is missing: check on site
Fully finishedfinished and ready to move inOnly what you want to change yourself

Older buildings do not use these words: people live there, and everything old has to come out first. That is why the SIVRCE calculator has five states — old stock, cosmetic refresh, black frame, white frame and fully finished.

Choosing the state is the calculator's first step: it decides which works enter the estimate by default. A mistake here costs half the estimate — which is why each state has a short explanation under its name.

Six rough works: who does them

The difference between a white and a black frame is six rough works. In a white frame the developer does them; in a black frame, you and your contractor do.

WorkBlack frameWhite frame
Floor screedYours to doDone by the developer
Wall plasterYours to doDone by the developer
Rough electricsYours to doDone by the developer
Rough plumbingYours to doDone by the developer
WaterproofingYours to doDone by the developer
PartitionsYours to doDone by the developer

The label is about the sale; the list of works is about the money. An apartment is sometimes sold as a "white frame" and handed over partly black — the screed or the plaster is missing. That is why the renovation estimate page lists these six works as separate checkboxes: tick what the developer actually did, and the estimate prices only the rest.

Demolition is not counted for a black frame — there is nothing to remove. Partitions are counted until you tick that the developer has already built them.

What it costs to finish the apartment

Prices for a 65 m² apartment in all three grades. They include labour, a materials allowance and additional costs (contingency, delivery of materials, waste removal — 10% in total).

GradeFrom a black frameFrom a white frame
Economy700 ₾/m² · 45,521 ₾440 ₾/m² · 28,578 ₾
Standard885 ₾/m² · 57,508 ₾574 ₾/m² · 37,288 ₾
Premium1,545 ₾/m² · 100,433 ₾1,132 ₾/m² · 73,605 ₾

In the Standard grade the gap is 311 ₾/m² — the price of those six rough works. Per-work prices are on the market prices page.

What to check when the developer hands over the keys

Before you call a contractor, walk the apartment and compare it with the contract:

  • Screed: is it poured in every room, and how level is it? Flooring cannot go onto fresh screed — a 50 mm layer takes about 42 days to dry.
  • Plaster: flatness over a 2 m straightedge — about 2 mm tolerance.
  • Electrics: is there a panel, and do cables reach every socket and light point?
  • Water and drains: are the points brought out in the bathroom and kitchen?
  • Waterproofing: in the bathroom, the floor plus 20 cm up the walls, up to 2 m at the shower.
  • Partitions: are all the walls shown on the plan actually built?

Whatever is missing has to go back into the estimate. Otherwise it surfaces in the first week — as "extra work".

Partitions in a black frame: aerated block or drywall

A partition is built from one material. On the SIVRCE price list (Standard), a square metre of aerated-block wall is 60 ₾ of labour and 37 ₾ of material; drywall is 75 ₾ and 37 ₾.

By default the calculator prices aerated block: it is the usual choice in a Tbilisi apartment, while drywall goes into light dry partitions. New partitions come to about 0.8 m² per square metre of floor. If the developer has already built them, tick that and the line leaves the estimate.

If a contractor's estimate has both aerated block and drywall over the full area, it is one wall counted twice.

Green frame: what to check at handover

In a green frame or an apartment finished by the developer you check the finishing work — the same points a SIVRCE inspector checks when accepting stages:

  • No hollow spots under tiles (tap test)
  • Even joints, neat cuts
  • Paint looks even in side light
  • Laminate doesn't creak, 8–10 mm gap at the walls
  • All sockets and lights work, no leaks

Record anything wrong before you sign the developer's handover act. If you want to change something — the kitchen, the paint, a partition — pick "Fully finished" in the calculator and tick only those works.

How long it takes

Renovating 65 m² from a white frame takes 69–91 days; from a black frame, 94–122 days (Standard grade, SIVRCE norms). Most of the gap is the screed drying: a 50 mm layer takes 42 days, and the finish flooring waits for it. How the timeline is calculated: the timeline guide.

The same words for houses and offices

A house is rarely called a "frame": in the calculator the same two states read "No interior finishes" and "With rough finishes" for a house, and "Shell and core" and "With rough finishes" for an office. The axis is the same — how much is already done — and so are the works left out.

For the order of works — why wiring goes before plaster and screed before flooring — see the guide to renovation stages.

Frequently asked questions

What is a white frame?

An apartment that is plastered, screeded, services roughed in — no finishes. Only the finishes are left.

How is a black frame different from a white frame?

By six rough works: screed, wall plaster, rough electrics, rough plumbing, waterproofing and partitions. In the Standard grade that is about 311 ₾/m².

What is a green frame?

A white frame with some of the finishes done; developers use the name for different things. The calculator has no separate state for it: choose white frame and untick what is already done — or "Fully finished" and tick only the work that remains.

Is bathroom waterproofing part of a white frame?

In the SIVRCE calculation, yes — it is one of the developer's six works. Check it on site anyway; if it is missing, untick it and waterproofing returns to the estimate.

Is demolition needed in a black frame?

No: there is nothing to remove, and the calculator does not count demolition for a black frame.

How much does it cost to finish a white frame?

For 65 m², about 37,288 ₾ (574 ₾/m², Standard, ±15%).